Bring the Plant and Supply Chain into PI Planning
- type
- proposal
- for-domain
- Charger ART
- derived-from
- Long-Lead Work Needs a Longer Horizon Than the PI
- status
- consented
- created_at
- 2026-10-05
Proposal
Two changes to how the Charger ART plans, from PI 27.1 on:
- Long-lead work is planned one PI ahead. At PI planning n, HW Base names every mold and long-lead part the features of PI n+1 will need; Supply Chain attends PI planning, takes the list, and the tooling dates go on the dependency board like any other dependency. Design freeze for a mold stays at the DFM Review, not at planning.
- The plant joins the release. The Manufacturing Lead becomes a participant of PI planning and the System Demo, not a guest; fixture work starts when a feature is demoed, not when the release package arrives; and a ramp-readiness check at every System Demo lifts the plant’s status back into the train.
Neither Supply Chain nor Manufacturing joins the ART as a team. They join its planning.
Objections
- Wen Zhao: committing to tooling one PI ahead means ordering molds for designs that may still change — addressed by committing the item and its date at planning and the geometry at the DFM review, where it is frozen today anyway.
- Greta Vossberg: two more parties make PI planning longer — accepted; the long-lead board is prepared before the event, not built in it.
- Marit Solberg asked whether this is the moment to give production its own FL2 or to merge it into the train’s board — deferred: run two PIs with the lighter change first.
Outcome
Consented at the Portfolio Sync on 2026-10-06. Recorded as Production Joins the Train’s Planning; operationalized by Long-Lead Commitment at PI Planning and Ramp Readiness Review, both in force from the PI 27.1 planning on 2026-12-03.