Expedite Lane Policy

type
agreement
agreement-type
work
for-domain
Charger ART
version
1.0
decision_date
2026-04-07
review_date
2027-04-06
created_at
2026-10-10

Driver and Requirement

In March 2026 a firmware fault left a depot of DC chargers dark for a weekend because the fix “would go into the next PI”. A charger that does not charge cannot wait ten weeks. The train needs one lane that bypasses the cadence — and a strict gate on what may use it, or the lane becomes the way everything gets done.

Who is responsible for what?

  • Field Service — reports every issue with its observed impact; does not rank.
  • The Field Issue Triage (product owners with Mateo Ruiz and Ravi Anand) — decides hotfix or feature, weekly; a safety issue is decided the same day, in a Safety Issue Call.
  • The team that owns the affected component — takes the hotfix immediately, at most one at a time.
  • Connectivity — ships the hotfix to the fleet over the air and confirms rollout.

Description

The Field Issue lane of the Charger ART Board is an expedite lane. An issue enters Fix-in-Progress only if it is a safety risk or a fleet is down — everything else becomes a Feature and goes to PI planning. WIP in Fix-in-Progress is two across the train, one per team: a second hotfix for the same team waits or is re-decided. Every hotfix is reported at the next System Demo.

Evaluation Criteria

  • Safety or fleet-down issues fixed in the fleet within five working days.
  • Fewer than one in five triaged issues enters the expedite lane — the rest travels as features.

Like what you see? → Start — build your own org folder in ~2 min

Expedite Lane Policy.md
---
type: agreement
agreement-type: work
for-domain: "[[Charger ART]]"
agreement-of:
  - "[[Charger ART Board]]#Charger ART/lane:Field Issue::in"
  - "[[Field Issue Route]]/stage:hotfix @ Train::before"
version: "1.0"
decision_date: 2026-04-07
review_date: 2027-04-06
created_at: 2026-10-10
---
## Driver and Requirement
In March 2026 a firmware fault left a depot of DC chargers dark for a weekend because the
fix "would go into the next PI". A charger that does not charge cannot wait ten weeks. The
train needs one lane that bypasses the cadence — and a strict gate on what may use it, or
the lane becomes the way everything gets done.
## Who is responsible for what?
- [[Field Service]] — reports every issue with its observed impact; does not rank.
- The [[Field Issue Triage]] (product owners with [[Mateo Ruiz]] and [[Ravi Anand]]) —
decides hotfix or feature, weekly; a safety issue is decided the same day, in a
[[Safety Issue Call]].
- The team that owns the affected component — takes the hotfix immediately, at most one at
a time.
- [[Connectivity]] — ships the hotfix to the fleet over the air and confirms rollout.
## Description
The `Field Issue` lane of the [[Charger ART Board]] is an **expedite lane**. An issue enters
`Fix-in-Progress` only if it is a safety risk or a fleet is down — everything else becomes a
[[Feature]] and goes to PI planning. WIP in `Fix-in-Progress` is two across the train, one
per team: a second hotfix for the same team waits or is re-decided. Every hotfix is reported
at the next [[System Demo]].
## Evaluation Criteria
- Safety or fleet-down issues fixed in the fleet within five working days.
- Fewer than one in five triaged issues enters the expedite lane — the rest travels as
features.