In March 2026 a firmware fault left a depot of DC chargers dark for a weekend because the
fix “would go into the next PI”. A charger that does not charge cannot wait ten weeks. The
train needs one lane that bypasses the cadence — and a strict gate on what may use it, or
the lane becomes the way everything gets done.
Who is responsible for what?
Field Service — reports every issue with its observed impact; does not rank.
The team that owns the affected component — takes the hotfix immediately, at most one at
a time.
Connectivity — ships the hotfix to the fleet over the air and confirms rollout.
Description
The Field Issue lane of the Charger ART Board is an expedite lane. An issue enters
Fix-in-Progress only if it is a safety risk or a fleet is down — everything else becomes a
Feature and goes to PI planning. WIP in Fix-in-Progress is two across the train, one
per team: a second hotfix for the same team waits or is re-decided. Every hotfix is reported
at the next System Demo.
Evaluation Criteria
Safety or fleet-down issues fixed in the fleet within five working days.
Fewer than one in five triaged issues enters the expedite lane — the rest travels as
features.