The FL1 board of the HW Base platform team — hardware work from concept to tooling release, in three column groups: Design, Verification, Release. The groups are the sub-processes a hardware change goes through, and the Verification group is where an agent works: the DFM Check Agent runs the design-for-manufacturing rules on every drawing that enters it, and the DFM Review with Manufacturing decides on its findings.

A card sitting in Tooling Released is not stuck: it is waiting out the fourteen weeks a mold takes — the lead time this whole example turns on.

title: HW Base
flightlevel: FL1
timebox: 2w
groups:
  - name: Design
    columns:
      - Backlog
      - name: Concept
        status-category: in-progress
      - name: Detailed Design
        wip: 3
        status-category: in-progress
  - name: Verification
    status-category: assess
    interactions:
      - "[[DFM Review]]"
    columns:
      - name: Design Review
        check: "Interface to both product lines confirmed with the System Architect"
      - name: DFM Check
        agreements:
          - "No drawing goes to tooling without a DFM review with Manufacturing"
      - name: Lab Test
  - name: Release
    columns:
      - name: Tooling Released
        status-category: waiting
        aging: 98d
      - name: Handed Over
        status-category: done
        check: "Drawings, BOM and test specification received by Manufacturing"

Modeling note

The DFM Check Agent is bound to the whole Verification group. Tooling Released is waiting with a long aging — the fourteen weeks a mold takes.

Like what you see? → Start — build your own org folder in ~2 min

HW Base Board.md
---
type: visualization
visualization-type: board
title: HW Base
visualization-of: "[[HW Base]]"
created_at: 2026-10-10
---
The FL1 board of the [[HW Base]] platform team — hardware work from concept to tooling
release, in three **column groups**: `Design`, `Verification`, `Release`. The groups are
the sub-processes a hardware change goes through, and the `Verification` group is where
an agent works: the [[DFM Check Agent]] runs the design-for-manufacturing rules on every
drawing that enters it, and the [[DFM Review]] with [[Manufacturing]] decides on its
findings.
A card sitting in `Tooling Released` is not stuck: it is waiting out the fourteen weeks a
mold takes — the lead time this whole example turns on.
```dwsd.board
title: HW Base
flightlevel: FL1
timebox: 2w
groups:
- name: Design
columns:
- Backlog
- name: Concept
status-category: in-progress
- name: Detailed Design
wip: 3
status-category: in-progress
- name: Verification
status-category: assess
interactions:
- "[[DFM Review]]"
columns:
- name: Design Review
check: "Interface to both product lines confirmed with the System Architect"
- name: DFM Check
agreements:
- "No drawing goes to tooling without a DFM review with Manufacturing"
- name: Lab Test
- name: Release
columns:
- name: Tooling Released
status-category: waiting
aging: 98d
- name: Handed Over
status-category: done
check: "Drawings, BOM and test specification received by Manufacturing"
```
> [!NOTE]
> **Modeling note.** The [[DFM Check Agent]] is bound to the whole `Verification` group.
> `Tooling Released` is `waiting` with a long `aging` — the fourteen weeks a mold takes.