PI Objectives Missed on Enclosure Tooling Twice
- type
- signal
- observes
- HW Base , Charger ART
- created_at
- 2026-09-23
In PI 26.2 and PI 26.3, one committed PI objective each — the wallbox enclosure variant, then the DC cabinet door — moved to the next PI because the injection-mold tooling arrived after the integration date. Both molds were ordered in week 3 of the PI; both took fourteen weeks. Raised at both Inspect and Adapt workshops.