Production Joins the Train's Planning
- type
- organizational-decision-record
- status
- accepted
- date
- 2026-10-06
- decision-makers
- Henrik Dahl , Ingrid Halvorsen , Marit Solberg
- for-domain
- Charger ART , Manufacturing
- derived-from
- Bring the Plant and Supply Chain into PI Planning
- created_at
- 2026-10-06
Context
Since the Charger ART was chartered in January 2026, Voltfeld has had two planning horizons that never meet: the train plans ten weeks of development; the plant and the supply base plan tooling and ramps that take longer than that, and learn about releases after the fact. Manufacturing contributes to the Portfolio directly — there is no FL2 that coordinates development and production together. Two PIs in a row, a committed objective slipped on a mold (PI Objectives Missed on Enclosure Tooling Twice); the 26.3 release shipped five weeks late because fixtures started at the release (Fixtures Built After the Release). The insight Production Is Outside the Train’s Horizon named the cause; the driver Long-Lead Work Needs a Longer Horizon Than the PI named the need.
Decision
Supply Chain and Manufacturing become participants of the train’s planning — PI planning and the System Demo — without becoming teams of the ART. Long-lead work is planned one PI ahead of the features that need it; ramp readiness is reviewed inside the PI, not after it. Operationalized by two agreements, Long-Lead Commitment at PI Planning and Ramp Readiness Review, and one role: Production Liaison, the plant’s seat at the train’s planning, kept by the Manufacturing Lead.
Explicitly not decided: no change to the units. Manufacturing stays in Operations, the plant does not join the ART board, and the question of a shared FL2 for development and production is deferred until two PIs have run under this decision.
The decision concerns two domains: the Charger ART, whose planning gains two participants, and Manufacturing, whose ramp now starts earlier.
Consequences
- The train commits to objectives whose tooling is already ordered — predictability should recover toward the 80% the PI Commitment asks for.
- The plant hears about a release at the demo and starts fixtures there: the five-week gap between release and first shipment should close.
- The Feature Route gains the edge it is missing today — ramp status flowing from the plant back into the train — once the agreements are in force.
- Trade-off: molds are committed a PI earlier, on designs frozen at the DFM review rather than fully integrated. Supply Chain carries that risk and said so.
- PI planning grows by two parties and about half a day.